词典论坛联络

   英语 +
Google | Forvo | +

schedule performance index

强调
大规模杀伤性武器 показатель эффективности графика
微软 индекс отклонения от календарного плана (The ratio of the earned value (EV), which is sometimes referred to as the budgeted cost of work performed (BCWP), to the planned value (PV), which is sometimes referred to as the budgeted cost of work scheduled (BCWS). SPI is often used to estimate the project completion date. The SPI value is calculated as follows: SPI = EV/PV. If the resulting SPI value is less than 1.0, that indicates that less work was completed on the project than was planned. If the SPI value is 1.0 or greater, that indicates that more work was completed than was planned; SPI; ИОКП)
项目管理 индекс выполнения сроков
 英语 词库
Schedule Performance Index
缩写, 大规模杀伤性武器 SPI
schedule performance index The ratio of the earned value (EV), which is sometimes referred to as the budgeted cost of work performed (BCWP), to the planned value (PV), which is sometimes referred to as the budgeted cost of work scheduled (BCWS). SPI is often used to estimate the project completion date. The SPI value is calculated as follows: SPI = EV/PV. If the resulting SPI value is less than 1.0, that indicates that less work was completed on the project than was planned. If the SPI value is 1.0 or greater, that indicates that more work was completed than was planned; SPI
缩写, 微软 SPI (일정 성과 지표)