comp., MS | key performance indicator | chỉ số hiệu suất then chốt (A predefined measure that is used to track performance of a strategic goal, objective, plan, initiative, or business process. A KPI is evaluated against a target. An explicit and measurable value taken directly from a data source. Key performance indicators (KPIs) are used to measure performance in a specific area, for example, revenue per customer) |
comp., MS | schedule performance index The ratio of the earned value (EV), which is sometimes referred to as the budgeted cost of work performed (BCWP), to the planned value (PV), which is sometimes referred to as the budgeted cost of work scheduled (BCWS). SPI is often used to estimate the project completion date. The SPI value is calculated as follows: SPI = EV/PV. If the resulting SPI value is less than 1.0, that indicates that less work was completed on the project than was planned. If the SPI value is 1.0 or greater, that indicates that more work was completed than was planned; SPI | chỉ số tiến độ thực hiện (SPI) |