afwijking bij voltooiing | variance at completion (The earned value field that shows the difference between the budget at completion [BAC] and the estimate at completion [EAC]. In Project, the EAC is the Total Cost field, and the BAC is the Baseline Cost field) |
afwijking hoeveelheid | quantity variance (The difference between an ordered product quantity and a received product quantity when no more receipts are expected) |
afwijking van planning | schedule variance (The difference between the budgeted cost of work performed [BCWP] and the budgeted cost of work scheduled [BCWS]. This is calculated as follows: SV = Budgeted Cost of Work Performed - Budgeted Cost of Work Scheduled) |
leveranciersgroep toegestane afwijking prijs, tolerantiegroep voor leveranciersprijs | vendor price tolerance group (A group that can be assigned to vendors and that controls the allowable price variance percentage for invoice matching) |
tolerantiegroep voor artikelprijs, artikelgroep toegestane afwijking prijs | item price tolerance group (A group of items that controls the allowable price variance percentage for invoice matching) |