Actual CapacityCapacitate efectivă (The amount of time a resource has available to work at any given point in time. Actual Capacity is equal to Capacity minus resource calendar exceptions (e.g. offsite training, morale events, jury duty) and previously scheduled committed work (Project task assignments with type = committed). This is the most valuable measure for scheduling a resource)
actual cost of work performedcost real al lucrului efectuat (The actual costs incurred for work already performed by a resource on a task, up to the project status date or today's date)
actual durationdurată reală (The amount of time a task has been in progress)
actual valuevaloare reală (A value for a KPI that is compared to a predefined target value)
actual worklucru real (The amount of work that has been performed on a task or assignment)