DictionaryForumContacts

   German
Terms for subject Microsoft containing berechnete Kosten | all forms | in specified order only
GermanEnglish
berechnete Kostenestimate at completion (The expected total cost of a task or project, based on performance as of the status date. EAC is calculated as follows: EAC = ACWP + (BAC-BCWP)/CPI)
Soll-Kosten der berechneten Arbeitbudgeted cost of work scheduled (The earned value field that shows how much of the budget should have been spent, in view of the baseline cost of the task, assignment, or resource. BCWS is calculated as the cumulative timephased baseline costs up to the status date or today's date)