German | English |
Soll-Kosten bereits abgeschlossener Arbeit | budgeted cost of work performed (The earned value field that indicates how much of the task's budget should have been spent, given the actual duration of the task) |
Soll-Kosten der berechneten Arbeit | budgeted cost of work scheduled (The earned value field that shows how much of the budget should have been spent, in view of the baseline cost of the task, assignment, or resource. BCWS is calculated as the cumulative timephased baseline costs up to the status date or today's date) |