Subject | English | Latvian |
comp., MS | early finish date | agrais beigu datums (The earliest date that a task could possibly finish, based on early finish dates of predecessor and successor tasks, other constraints, and any leveling delay) |
comp., MS | finish date | beigu datums (The date that a project or task is scheduled to be completed. This date is based on the task's start date, duration, calendars, predecessor dates, task dependencies, and constraints) |
comp., MS | late finish date | vēlais beigu datums (The latest date that a task can finish without delaying the finish of the project. It is based on the task's late start date, as well as the late start and late finish dates of predecessor and successor tasks, and other constraints) |